This past week was pretty uneventful but we do have good news to report.
First, our carrier has finally completed the installation and testing of of the new GiGE connection. WE are now just waiting for them to get the capacity added to the circuit and then handed over to us for our testing. We are hopeful that we will be up on the new GigE connection by mid-week 12/10/08.
On the Exchange 2007 front, the SAN has finally come in. We've not even opened the box yet, but at least now we can schedule the NetApp engineers to come in and work with us to get it configured and into production. We will coordinating the scheduling next week. We are hopeful that we will be rolling forward the week of 12/15.
Data Center and Network Up Time
Data Center and Network Up Time from 11/28/08 5PM to 12/5/08 5PM was 100%.
There were no unexpected NET1Plus Production server outages for the same period.